Coordinating Three Highway Designs Into One Deliverable Scheme
TDS was appointed to provide project management and design coordination support for a complex Section 278 highways scheme at New Road, Hellingly.
The project involved three separate junction improvement packages that had originally progressed as individual designs but needed to be reviewed together as one coordinated and deliverable scheme.
The challenge was to bring clarity to the interfaces between the designs and establish a single route forward for approvals, tendering and pre-construction planning.
Bringing the Design Packages Together
TDS acted as the central coordination point across the three junction improvement packages, reviewing how the separate designs and technical inputs interacted and managing the actions required to move the scheme towards a coordinated position.
A Coordinated Route Towards Delivery
The three junction improvement packages have been brought into a coordinated design position, giving the project team a much clearer basis for technical approval, legal agreement, tendering and future delivery.
The three junction improvement packages have been brought into a coordinated design position, giving the project team a much clearer basis for technical approval, legal agreement, tendering and future delivery.
The client now has greater confidence in the route towards construction, with reduced interface risk and a clearer understanding of the remaining technical, commercial and delivery requirements.
Brought together into one coordinated design position
Technical inputs coordinated across the wider Section 278 scheme
A stronger basis established for approval, tendering and construction