Resolving Legacy Infrastructure Issues Across a Major Development
TDS was initially instructed between 2018 and 2020 to investigate infrastructure issues across the four-phase Eco-Town development in Bicester. Investigations identified multiple sources of infiltration within the sewer network, leading the water authority to require extensive remedial works, including the excavation and complete rebuilding of a number of manholes.
Following remedial works and further investigations in 2019, progress was interrupted by the Covid-19 pandemic. TDS was re-instructed in 2024 to progress the outstanding infrastructure requirements, beginning with the commissioning of the development’s large pump station, designed to serve approximately 2,000 homes.
Coordinating the Route Through Remediation and Adoption
Following re-instruction in 2024, TDS established a coordinated programme to progress the outstanding infrastructure requirements across the development. The initial focus was commissioning the large pump station before moving on to the wider Section 104 sewer network and Section 38 highways, working with the relevant authorities and contractors to move each element towards completion and adoption.
Major Infrastructure Milestones Achieved
Since being re-instructed in 2024, TDS has helped progress a series of significant infrastructure milestones across the Eco-Town development. The pump station was successfully commissioned in January 2025, followed by completion of the wider Section 104 sewer works in early 2026.
Section 38 highway works are now progressing across the development, with the current programme supporting Maintenance Certification for three of the four phases. Through liaison and negotiation with the Local Highway Authority, TDS has also secured a reduction in the extent of surfacing required, delivering an estimated saving of approximately £150,000 for the client.
Pump station commissioned, Section 104 sewer works completed and approximately £150,000 saved through negotiation of the highway surfacing requirements.
The development’s major pump station, designed to serve approximately 2,000 homes, was successfully commissioned in January 2025.
The outstanding sewer works across the wider development were completed in early 2026, marking another significant step towards resolving the site’s legacy infrastructure requirements.
TDS negotiated a reduction in the extent of highway surfacing required by the Local Highway Authority, delivering an estimated saving of approximately £150,000 for the client.